Correct time entries
Review correction requests for stamps, approve or reject them with a reason and correct entries directly
→ Open correction requests in SimpliServ · Open the time clock
Corrections are meant for existing stamps: a forgotten clock-out, a wrong time, a missing break. Every change needs a reason, the original value stays in the correction history.
Permission and period
The Correction requests page under Scheduling requires Attendance → Manage. If an entry lies in an already closed month, it can't be changed – the interface then shows Period is closed and locked.. The month must first be reopened in the month close.
Review a correction request
The table shows Employee, Entry, Changes (old → new for start, end, breaks, note), Reason, Requested at and Status.
Open requests first
Sort by status Pending.
Check staff member and day
Compare date, shift in the roster and existing stamps.
Understand the change
Read old and new values and the reason. Ask back if it overlaps with leave or another shift.
Decide
Approve applies the change, Reject leaves the entry unchanged. In the dialog you can leave a Comment (optional) for the staff member.
Check the result
Open the entry on the time clock page and check duration and correction history.
Read the status
| Status | Meaning |
|---|---|
| Pending | decision open |
| Approved | correction applied |
| Rejected | correction not applied |
Correct directly
Without a request you correct with Attendance → Manage on the time clock page: expand the entry and choose Correct, change start, end, breaks or note and enter a Reason. If an entry is missing entirely, you add it with Add stamp. With Cancel entry a wrong entry stays visible with a cancellation note but no longer counts toward the totals.
Don't approve a correction without a reason and a cross-check. Working time data flows into balance, surcharges and the compliance check.
Monthly check
- No open requests left, or deferred with a reason.
- Rejected requests have a comment.
- Approved times appear in the time report.
- Closed months stay unchanged.